
|
The site is inspected, and sometimes safety modifications are made
even before the ride ever runs. Notice the track steel still needs to be added.
|

|
Here is a good example of what I mentioned earlier about how it gets
harder and harder to maneuver a crane through the construction site after much of the
structure is already constructed.
|

|
| On areas of track that are subject to excessive side movement
that the structure itself would be unable to support, support cables or "wire
ropes" are used to add stability to these areas. Above, you see the center of a
fan curve that is one of these areas of excessive side movement, which is why the concrete
pillar is seen in the right side of the photo. Metal anchors have been submerged
into the concrete, and will soon fasten to several cables that will stretch up to the
inner edge of the upper coaster legs. |

Here is the beginning of the transfer track. Each coaster has certain parts that
always seem to end up different. This is one of those parts. This particular
transfer track uses inverted angle iron (upside down V shape), which you see on top of the
support ledgers above, and the rolling transfer table will use special V-shaped steel
wheels. The track rolls from side to side, and then the train is rolled from/to the rear
holding area. (not built yet in this photo)
|

Regardless of the winter or wet weather, these guys are always out working, because
there's usually no time to waste. Parks will not normally begin a construction project
mid-summer, and yet they always want it done for you by opening day, so it only leaves
about 6 months at the most to build a coaster, and these guys build more than one coaster
in a winter! Rough job!
|